Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

The Negatives of Negative Lag

2 replies [Last post]
Emily Foster
User offline. Last seen 2 years 25 weeks ago. Offline
Joined: 19 Aug 2011
Posts: 625
Groups: None

A good discussion on the negatives of Negative Lag ow.ly/MGQeX

Replies

Emily Foster
User offline. Last seen 2 years 25 weeks ago. Offline
Joined: 19 Aug 2011
Posts: 625
Groups: None

Many thanks for your response to our article.  Indeed we agree, there are many instances where negative lags are appropriate and the article you provided a link to was certainly an interesting and detailed look at the history and usage of such links. 

To give you a little context that was not very apparent our article, the blog we posted was partly in response to a trend within certain government agencies to actually rule out the use of leads in schedules submitted to them as part of a DOD or DOE program.  And we wanted to underline some of the reasons for this stance.  Indeed we’ve seen language specifically banning their use in some recent government contracts.  This is rather disturbing as it moves these items out of the scheduling guidelines column and places them squarely in the scheduling rules column.  One such contract not only banned the use of Leads, but also banned Lags, and any relationships type other than Finish-to-start.  It was extremely restrictive and hobbled the scheduler’s ability to model certain elements of the project accurately.  Because we work with mostly Primavera P6 in the DOD and DOE contract world, I myself do try to minimize the use of leads simply to avoid blowback.  Ultimately, I believe it behooves the individual scheduler to model the schedule using whatever tools necessary to represent the work most realistically.  If they can defend it rationally, then it’s probably the right kind of link.

Thanks again for your interesting perspective on this somewhat controversial topic.  We appreciate your feedback.

Patrick Weaver
User offline. Last seen 4 days 20 hours ago. Offline
Joined: 18 Jan 2001
Posts: 383
Groups: None

The link is to a good basic discussion but not a good example.......

As with all planning options firstly it depends on the tool you are using and then on any imposed limitations.  Negative lags (or leads) are useful particularly for small ovrlaps associated with a handover.  The type of 'progressive feed' example discussed in the post is much better dealt with using 'ladders' or some type of relationship that reflects the progress of work in the lead activity. For more on this see: http://www.mosaicprojects.com.au/PDF/Links_Lags_Ladders.pdf