Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Contractor denies to submit Revised Clause 14.1 Program for 2 YRS

2 replies [Last post]
G. kumar
User offline. Last seen 7 years 18 weeks ago. Offline
Joined: 1 Jul 2004
Posts: 9
Groups: None

Dear All,

Our Road/Brodges project with Original Duration of 2 yrs costing 5bn UAE Dirhams was started in Jan 2012. Contractor submitted CL14 programme within 28 days from work order.  But the scope of work was keep on inceasing from time to time and the project cost increased to 7bn. Taking this as an oppurtunity contractor was denying to submit the Revised CL14.1. Consultants ascertained that Scope of work may increase or decrease in the course of time, but contractor is bound to submit a revised work programme. but he is insisting for the final BOQ. Please assist me for pushing the contarctor to get the revised baseline. Ty.

Regards,

Kumar 

Replies

Mike Testro
User offline. Last seen 36 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Kumar

If the contractor is not complying with his contractual obligations the Engineer can reduce interim payments until he does.

Best regards

Mike Testro

Rafael Davila
User offline. Last seen 2 weeks 18 hours ago. Offline
Joined: 1 Mar 2004
Posts: 5241