Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

planned & actual S-curve VS EV

1 reply [Last post]
moh ham
User offline. Last seen 9 years 16 weeks ago. Offline
Joined: 3 Mar 2011
Posts: 8
Groups: None

Kindly advice if the client have the right to request from the contractor to show his resources in the submitted schedule , in case if he hasn't the right how the client or the consultant can evaluate the actual s curve and the EV.

Thank you

Replies

R. Catalan
User offline. Last seen 12 years 43 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 314
Groups: None

Hi Moh,

Submission of allocated resources is already part of the Constractor's daily report. If is tiresome for the Contractor to reflect the actual resources in the schedule, he can request to do it in spreadsheets format (MS Excel) as it would be easy for him to link to other reports (daily report, resource histograms, etc.).

On typical contract scheduling requirements, the Client has the right to request the Contractor to show his resources in the submitted schedule..

Best regards,

R. Catalan