Hi Brij
Thank you for this input - a few queries:
Why stop at tack welding - there should be at least two more passes?
Who takes the scaffolding down?
When does the integrity test happen?
Best regards
Mike Testro
Dear Brij,
Please find out the piping erection on site & also other materails E.g SS316,Duplex, CS Molybdenum etc.
Site Productivity Formula.
Thanks for above information & waiting for other technical information regd the piping norms.
Regd,
Majid
Dear Brij,
This is a good idea and should be added into the dedicated section (Rates).
One comment anyway, I think we should not integrate contingency into the ratio. Usually contingency are added after the MHrs calculation on an overall quatity.
 
 
Rgds,
 
Maxime.
Hi Brij Thank you for this
Hi Brij
Thank you for this input - a few queries:
Why stop at tack welding - there should be at least two more passes?
Who takes the scaffolding down?
When does the integrity test happen?
Best regards
Mike Testro
Dear Brij, Please find out
Dear Brij,
Please find out the piping erection on site & also other materails E.g SS316,Duplex, CS Molybdenum etc.
Site Productivity Formula.
Thanks for above information & waiting for other technical information regd the piping norms.
Regd,
Majid
Dear Brij, This is a good
Dear Brij,
This is a good idea and should be added into the dedicated section (Rates).
One comment anyway, I think we should not integrate contingency into the ratio. Usually contingency are added after the MHrs calculation on an overall quatity.
 
 
Rgds,
 
Maxime.
Sameway it can be found out
Sameway it can be found out for welding, supporting, testing and structural steel erection activities.