Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Ladder relationship and critical path

13 replies [Last post]
Balu Karunakaran
User offline. Last seen 12 years 25 weeks ago. Offline
Joined: 16 Dec 2007
Posts: 32
I want to make some of my activities deliberately in the critical path.Is there any method for that.

What is the use of ladder relationship.ie ss with ff relationship.

Replies

Tanveer Ahmad Niazi
User offline. Last seen 6 years 35 weeks ago. Offline
Joined: 15 Dec 2005
Posts: 151
Groups: GPC Qatar

hi, I am new in the forum and in planning as well, can any one tell me about "Claim Digger" in the forum or by tanveeraniazi@yahoo.com, Thanx

Naveen Paladugu
User offline. Last seen 8 years 7 weeks ago. Offline
Joined: 7 Jul 2010
Posts: 47

Can we call this as Schedule Analysis?

Stephen Devaux
User offline. Last seen 2 weeks 2 hours ago. Offline
Joined: 23 Mar 2005
Posts: 668
In terms of not using calendar-based constraints, I agree with Mike 99.9%. The one exception is if a constraining factor is TRULY calendar driven (e.g., for some reason, you HAVE to wait for the full moon, or for a comet to reach a certain point), and you know EXACTLY when that will occur.

But if you DO use constraints, two rules to follow:

(1) Input each constraint separately, one at a time, and see what the impact is. If you can’t live with the impact of a specific constraint, you’re going to have to figure out a way around it.

(2) FILTER OUT all constraints (and LOEs!) when doing what-ifs and other schedule analysis. The constraints will constrain (!?) your (and the software’s) ability to push things around and see the impact.

For example, constraints and LOEs will erroneously change the drag calculations in MSP (and I suspect in Spider Project -- Vladimir?).

Finally, as has been said, the issue of playing around with float is a dangerous game. And, as for highlighting all activities with less than a certain amount of float, sure, do that if it reminds you to keep track of paths with limited float.

But ultimately, what’s important to project completion is drag -- if the second longest path has 5D of float, that means the CP tasks at that part of the schedule can have up to 5D of drag. That’s crucial info -- use it NOT to justify "pacing" the project and letting the second longest path slip by 5D, but to pull in the longest path by 5D or more. And then iterate the process on whatever activities are now on the longest path.

This optimization process is crucial -- if my project MUST be completed by June 30, I’d much rather have a schedule where the longest path is scheduled for completion June 10 and there are 12 other paths with less than 5D float than a schedule where the longest path is scheduled for completion June 29, and the next 12 longest paths all have 15D - 20D float. And that’s how you generate your schedule reserve.

Fraternally in project management,

Steve the Bajan
Mike Testro
User offline. Last seen 36 weeks 3 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Sergey

Welcome to Planning Planet.

We look forward to further contributions.

You may be interested in the Spider Software threads.

Best regards

Mike Testro
Sergey Prazdnikov
User offline. Last seen 13 years 2 weeks ago. Offline
Joined: 21 Jun 2010
Posts: 4
I agree not to use constrains at all. Otherwise it’ll break schedule logic.
I suggest you should change the criteria of critical path.
Put total float <= 5 days or 10 days (instead of default total float <=0) In that case all near critiacl activities come to the critiacal path and become "red" on the gantt chart. It is also give you some additional time (Float) to control activities before they become really critical.
Shah. HB
User offline. Last seen 49 weeks 3 days ago. Offline
Joined: 25 Nov 2008
Posts: 773
Hi to all

Mandatory start constraints set both early and late dates equal to the specified date.This constraint tends to overwrite all calculated results in the schedule
Mike Testro
User offline. Last seen 36 weeks 3 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Mukunda

And then what happens to the critical path.

Never use any constraints at all.

Best regards

Mike Testro
mukunda y
User offline. Last seen 11 years 10 weeks ago. Offline
Joined: 12 Nov 2008
Posts: 97
Groups: None
Bala

If u want to show the activity as a critical path put the constraint must start. it will make float to 0
sherif saied
User offline. Last seen 14 years 37 weeks ago. Offline
Joined: 13 Nov 2009
Posts: 13
hi samer , i got a difficult puzzle as a CPM network if u r interested i can send it to u via email to solve it if u can???
Mike Testro
User offline. Last seen 36 weeks 3 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Samer

Surely you need to make the starting date later for it to become critical sooner.

Another way is to delete all links and put a must end by flag on every task.

I re state - it is bad practice to fiddle a programmes critical path.

Best regards

Mike Testro
Samer Zawaydeh
User offline. Last seen 5 years 38 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Balu,

You can do that by making their float = 0. Any way you can think of achiving that.

The activity will become critical if you do not work on it at the right time and when its float is zero. You might want to try to change the starting date to an earlier date. This will make it become critical faster.

With kind regards,

Samer
Shah. HB
User offline. Last seen 49 weeks 3 days ago. Offline
Joined: 25 Nov 2008
Posts: 773
Hi

Use of ss and ff links together holds good to shift non activities to crticial
Mike Testro
User offline. Last seen 36 weeks 3 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Balu

Why do you want to fiddle your programme to make an articial critical path?

There are many threads on ladder programmes for you to search your answer.

Basically ladders are good for production line factory programmes with lots of repetion - they are of little use in construction.

Best regards

Mike Testro