Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

% Doubt

4 replies [Last post]
Shah. HB
User offline. Last seen 1 year 4 weeks ago. Offline
Joined: 25 Nov 2008
Posts: 773
Hi to all

I saw a report ,in the target date box which is highlighted in the first page,in that they mentioned details as shown

1. Total duration of the project [assume=480 days]
2. Days Elapsed [assume=680 days]
3. % of Elapsed Period [141.67%]

The way of representing 141.675% is correct?> since in mentioning numbers in percentage i thrust it shouldn’t be greater than 100

Replies

Shah. HB
User offline. Last seen 1 year 4 weeks ago. Offline
Joined: 25 Nov 2008
Posts: 773
Thanks to all
R. Catalan
User offline. Last seen 12 years 46 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 314
Groups: None
Shahul,

Though calculation is correct the way % is presented is misleading.

I agree with Samer, but maybe you define more by showing
a) % submitted
b) % approved

Best regards,

R. Catalan
Samer Zawaydeh
User offline. Last seen 5 years 46 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Shahul,

This is a very rough way to present the information. You need to have several additional block to fill in order to determine which side is delaying the works.

1. % of Material submittals completed
2. % of Shop drawings completed
3. # of RFIs sent
4. # of Confirmation of Verbal instructions
5. % invoices
6. % of invoicing under progress
7. # of approved variation orders and value
8. # of pending varaiation orders and value
9. # of design changes
10. % Long lead items arrived at site

It is better to review the type of project and determine the best criteria to monitor it. After all, you need to use the information you present in order to take the right decisions.

With kind regards,

Samer
Anoon Iimos
User offline. Last seen 3 years 4 days ago. Offline
Joined: 22 Sep 2006
Posts: 1422
the calculation is correct, it will only depend on how you’ll interpret the figure