cbs /obs

4 replies [Last post]
Milind Pandhare
User offline. Last seen 8 years 38 weeks ago. Offline
Joined: 29 Aug 2005
Posts: 54
Groups: None
hello friends as a planning engineer i know WBS
but what is CBS /OBS????

Replies

Omar Grant
User offline. Last seen 15 years 36 weeks ago. Offline
Joined: 25 Sep 2005
Posts: 71
Regardless of the terminology used all projects need a coding structure which, apart from other uses, provides a link between the cost estimate, project budget and project schedule. If done with common sense and not ’hi-jacked’ by SAP type accountancy requirements (which usually differ from the facility/equipment view of an engineer)it becomes a fairly simple matter to relate tasks in the schedule to their appropriate costs/quantities in the estimate/budget. I find recently that Clients using SAP systems often ’impose’ WBS structures that are based on cost accountancy formats and do not suit the way engineers view a project structure.
Peter Holroyd
User offline. Last seen 1 day 22 hours ago. Offline
Joined: 6 Jun 2005
Posts: 165
You can also add a useful Contract Breakdown Structure for Alliance or Partnering jobs if one Company is doing several parts of the job under different contracts. You need to choose software that allows you to have multipule hierarchical structures rather than just one WBS
Brennan Westworth
User offline. Last seen 7 years 30 weeks ago. Offline
Joined: 23 Feb 2003
Posts: 150
Groups: None
cbs is cost breakdown structure, this is allows you to break down the costs (thats right) cost breakdown structures allow accountants and cost engineers to break down the project into elements that are easy for them to forecast and track.

obs is the organisational breakdown structure and is determined by responsibility.

meh... its all bs to me :D
Bernard Ertl
User offline. Last seen 9 years 50 weeks ago. Offline
Joined: 20 Nov 2002
Posts: 757
Sciforma has published a short paper by Harvey Levine discussing differences in the WBS, OBS and RBS: Do You Weebis?

Bernard Ertl
InterPlan Systems