Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Define Total Project Percentage on EPC Projects

19 replies [Last post]
Tony Shelton
User offline. Last seen 20 years 22 weeks ago. Offline
Joined: 20 Dec 2002
Posts: 4
Groups: None
How is the total project percentage calculated on Engr-Procuremnt-construction (EPC) projects? Is basis on financial solely or some other method? Would like to see how others are doing it.

Replies

Forum Guest
User offline. Last seen 17 weeks 5 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
With regards to EPC, normally the weight for P is the most higher, then, C and E is the least (based on the cost)
For a particular project, i.e. in Oil & Gas industry, it started out with E, and about 30% or so the P will pick-up and then at about mid way the C begins. Therefore, I guess the weightage based on cost is the most appropriate, it starts low and pick-up as the P started and will never reached a point unles all the matls & eqpts being delivered. It will only finish off when the construction finishes.


Forum Guest
User offline. Last seen 17 weeks 5 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
hi,
from reading all the replies, i think the discussion is genrally about the measurement of performance in EPC Contracts and to see if all tasks are being completed on schedule. the perimeter for the measurement of performance is percentage complete.
i am working on the claim involing extension of time. as i have to mimic the actual schedules made by the subcontractor, the calendar variations and use of different softwares really creates a porblem e.g. CS Project schedules the activities for the same day as its predecessor finishes (I havent cleared out the concept Why it happens). so the durations of these tasks vary as calendars and start, finish dates vary.
for the calculation of performance, i have two options:
1-look for a time slice when a large number of activities was complete. or
2-evaluate the percentage complete of a particular activity and use it.
amazingly, the resluts appear quiet close to what the actual performance was. SO i would say that percentage complete does help.
Safdar H. Hashmi
Hal Macomber
User offline. Last seen 20 years 38 weeks ago. Offline
Joined: 15 Jan 2003
Posts: 9
Groups: None
The PPC measurement is not designed to make you look bad when you don’t finish. It just works out that way! Actually, the people use the measure as a tracking metric. You want to see improving PPC on a week-to-week basis. If that is the case, then the team is managing their work. If PPC is flat or declining then there’s something the team needs to be learning. I’ve seen teams that approach achieving PPCs in the 90s as they get close to the end of their projects.
Ernesto Puyana
User offline. Last seen 8 years 13 weeks ago. Offline
Joined: 12 Jan 2001
Posts: 111
Groups: None
Your reflection is absolutely valid. That is why my percent complete figures regress from week to week, when not only activities planned have not been completed, but remanent durations extended time over time.

Unless you finish what you planned, the measurement will make you look bad. That’s what is is for. isn’t it?

Forum Guest
User offline. Last seen 17 weeks 5 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
Out of simplicity, I’ve been using the time based project percent complete that Suretrak calculates from activity percent complete data I provide weekly. In general, it seems to work quite well, except when there is a substantial delay, which can generate a reduction in percent complete.
Has anybody noticed this? I’m I using the wrong parameter?
Hal Macomber
User offline. Last seen 20 years 38 weeks ago. Offline
Joined: 15 Jan 2003
Posts: 9
Groups: None
It depends on what you are looking to calculate. The usual percent complete measure addresses how much effort has been expended vs. how much effort was planned. One of my friends puts it this way, "THat’s why when you are 90% coplete, you still have another 90% to go!" She means that expending effort is not the same as producing results.

The Microsoft MS Project development team noticed this a few years back when they were updating the s/w. The team leader decided to have the project team use ’Project 2000’ as the tool for developing ’Project 2002’. After only a few short weeks team members wanted off the project. They learned a number of lessons which you can read about at http://halmacomber.com/jammin/2002_08_25_archive.html#80714453. One of the more important lessons is monitoring completion. Tracking expended effort vs. planned effort they concluded was useless. They track percent of tasks completed as planned to be completed.

In the construction world the approach is know as plan percent complete (PPC). The team tracks on a daily basis did they finish the work they planned to be finished on a daily basis. 99.5% complete is considered incomplete. You either got it done or not. You got no credit for completing work that was not planned for that time.

This method brings attention to two key aspects of projects that Eli Goldratt speaks about in the Theory of Constraints: dependence and variability. The start of my work depends on the completion of your work. If I am to start without delay, then you must complete when you promise. The PPC measure places an emphasis on completing as promised rather than the effort to perform.

Hal
http://weblog.halmacomber.com
Mehdi Rashidi Ala...
User offline. Last seen 9 weeks 4 days ago. Offline
Dear morteza,
As you know cost factor is very stable for PM in the Oil & Gas Projects.
In the fact any items convert to cost factor.

your comment?
Morteza Jafari
User offline. Last seen 12 years 19 weeks ago. Offline
Joined: 20 Jul 2003
Posts: 33
Hi Guest
I accepted your experiance and I think you shall not insist to be Weight factor based on cost,
what is your idea sombody else ?
Forum Guest
User offline. Last seen 17 weeks 5 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
Hello,
I have a bad experience in this regards, I worked in EPC project in previouse project, , that project P was 90% based on cost, but actually most value of project was construction when work went to construction phase project had 82% our managers satirized us progress was very funnyfrom view of Time, P took 3 months but construction was done 12 months !! project director punished Planning group for this wrong actually that was not wrong it was correct based on cost !
Mehdi Rashidi Ala...
User offline. Last seen 9 weeks 4 days ago. Offline
Dear morteza,
You are right. but for coordination & normalization between items ( such as EPC items) cost factor ( with all of them, such as material, manpower , ... ) is better.

M.Rashidi
Forum Guest
User offline. Last seen 17 weeks 5 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
Dear morteza,
You are right. but for coordination & normalization between items ( such as EPC items) cost factor ( with all of them, such as material, manpower , ... ) is better.

M.Rashidi
Morteza Jafari
User offline. Last seen 12 years 19 weeks ago. Offline
Joined: 20 Jul 2003
Posts: 33
dear, I advise to useing manhours base if you have it give the best weight factor in project, cost base may give the wrong progress dring exceution project, because you are seeing everything from view of cost not physical.
Mehdi Rashidi Ala...
User offline. Last seen 9 weeks 4 days ago. Offline
Dear my friends,
You must calculate weight of this items ( E & P & C) with cost norm and then calculate Progress report.

Regards
Forum Guest
User offline. Last seen 17 weeks 5 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
[dulplicate post]
Forum Guest
User offline. Last seen 17 weeks 5 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
I have written an paper on the practical applications of Earned Value Performance Measurement which outlines some of the issues discussed here, you will find it under the heading "Technical Papers".

There are a number of percentage completes that may be calculated and they all provide a different view of the project.

Typically I discuss:
1. % of Hours
2. % of Costs
3. % of Deliverables produced in terms of Cost or Quantity.
4. % of Time expended

These percentages may be presented as
1. % Original Budget
2. % of Current Budget
3. % Forecast Cost at Completion.

The ones that are monitored very much depend on the drivers of the project:
1. Is the project time, cost, resource or risk sensitive?
2. Are you the client or the contractor or is it an inhouse project.

Regards

Paul E Harris
Eastwood Harris Pty Ltd
Hal Macomber
User offline. Last seen 20 years 38 weeks ago. Offline
Joined: 15 Jan 2003
Posts: 9
Groups: None
Tony,

I work with a number of EPC contractors. There is a shift underway away from using these weighted performance measures. Even Microsoft has noted the limited value of percent complete data. See: Microsoft Eats the Dog Food. The conclusion contactors are reaching is we must measure the completion of work according to plan rather than the progress of work usually in hours applied versus planned. The first is a measure of reliability. The second is often construed as a predictor of performance.

The measure for plan reliability percent of plan complete (PPC) is easy to use. Calculate the percent of tasks completed as planned in a time period. For instance, 2 tasks planned for completion each day during the week. Lets say the two tasks were missed on Monday, but all other tasks were completed on the days planned. The performance would be 80%. Performance can be calculated by major performer (specialty contractor) and aggregated without dealing with averages of averages.

The principal reason firms are moving to this measure is task starts (and finshes) on projects usually depend on the completion of other tasks. The PPC measure addresses the fundamental variable in improving the flow of work on the project.

Hope this helps.
Tomas Rivera
User offline. Last seen 5 years 35 weeks ago. Offline
Joined: 2 May 2001
Posts: 139
Groups: None
Tony:

I think you are refering to the weighting method or weight factor for assessing the value of activities for progress evaluation.
There is a good discussion about this subject in the Planning, Scheduling and Programming Discussion forum under the title "Weight Factor". It might answer your question.

Tomas Rivera
Tony Shelton
User offline. Last seen 20 years 22 weeks ago. Offline
Joined: 20 Dec 2002
Posts: 4
Groups: None
The total combination of engr. complete, procurement complete, and construction complete. Financial completion is easily calculated. I am looking for what other EPC contractors are utilizing if at all. Do they have owners and PMs asking for this information? Beyond the financial answer, I not sure how you might show or calculate the value, or if it would trully be meaningful.
Tomas Rivera
User offline. Last seen 5 years 35 weeks ago. Offline
Joined: 2 May 2001
Posts: 139
Groups: None
Tony:

What do you mean by total project percentage?

Tomas Rivera