Different Durations for Activities & WBS

1 reply [Last post]
Ashik GB
User offline. Last seen 7 years 22 weeks ago. Offline
Joined: 10 Dec 2010
Posts: 27
Groups: None

Hello EVerybody,

Hope everybody were doing well.

I have a small complexicity while doing a schedule. When some activities entered under a WBS with proper durations and relationships.

But after scheduling, I found the WBS durations are less than the project durations and i have checked the calenders that i assigned for activities & projects and even WBS also.But still the problem is same.

Can any body will suggest to get out of this problem and the calender i have given is 7 days working with 8hrs/day 

Regards,

Ashik

Replies

Abilash Palakkada...
User offline. Last seen 8 years 38 weeks ago. Offline
Joined: 25 Aug 2012
Posts: 47
WBS duration will be the the tenure of the activites under that particular WBS.