Copy Activities between projects having different WBS

6 replies [Last post]
Hamza BENOUFIR
User offline. Last seen 18 weeks 7 hours ago. Offline
Joined: 22 Jan 2020
Posts: 18
Groups: None

Hello,

Currently trying to update a master baseline draft, I'm trying to update and add some activities to the MS from another project, but both have different WBSs. Is there a solution or I'll have to manually update?

 

Thanks.

Replies

Zoltan Palffy
User offline. Last seen 3 days 9 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

Open both projects 

make sure that you are in the WBS folder then copy activites from 1 project to the other 

Bian Mutang Tagal
User offline. Last seen 3 years 5 weeks ago. Offline

Hi Hamza,

Probably you could try a quick verification on your side using the Update Baseline feature as suggested by Zoltan and see what happens (make a backup of your draft baseline first). 

The baseline to attach is basically your master baseline draft.

Hamza BENOUFIR
User offline. Last seen 18 weeks 7 hours ago. Offline
Joined: 22 Jan 2020
Posts: 18
Groups: None

Since I'm still developping the Baseline, no BL is attached yet.

Hamza BENOUFIR
User offline. Last seen 18 weeks 7 hours ago. Offline
Joined: 22 Jan 2020
Posts: 18
Groups: None

I haven't explained the case well, I opened both projects, the activities in both share the same activity IDs, names etc.. (minus a few exclusions). The difference is that the WBS where these activities are stored under.

For example

Project (Old) : Activity 1 is under WBS 1.1.1

Project (New) : Activity 1 is under WBS 1.2.1.1

The problem is that There are many activities like this stranded accross multiple WBS. (I can filter them in the activities tab).

Santosh Bhat
User offline. Last seen 14 weeks 6 days ago. Offline
Joined: 15 Apr 2005
Posts: 381

Have you opened both projects at the same time? You can then Group by WBS or any common Activity codes they may share.

Zoltan Palffy
User offline. Last seen 3 days 9 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

if there is a baseline attached then you can go to Maintian Baselines and select Update

from here you can tell it what you wabt updated check the second section where it says Add new activities and activity data 

Uncheck update exiting activities already in the baseline 

then select Update options and select General Activity information 

activity code assignments 

relationships

WBS assignmnets and anything else listed

then select Update 

you will receive a message Update process complete

check your results