Hi everybody,
I searched the forum but did not find the answer I'm looking for.
I have a 6 hour activity (in an 8 hour day) that I need to start and stop on the same day. The curing time does not allow me to continue the next morning. I've assigned some resources to this activity, equipment and labour.
The problem I have is that it's predecessor ends around noon. When I schedule the project it splits it over 2 days.
My projects are fairly standard in terms of the sequence of activities. This activity is repeated for nearly every project I create. I know that I can introduce a lag, but I would rather avoid it if possible. I fear that I would have to go back and edit the lag for each project everytime I add a new one that uses the same resources.
A nudge in the right direction is greatly appreciated.
Thank you in advance for your assistance
Using Primavera P6
Skill Level : new to Primavera
Replies