How to revise budget unit without changing the current duration???

14 replies [Last post]
Ali Reza
User offline. Last seen 6 years 34 weeks ago. Offline
Joined: 15 Mar 2017
Posts: 18
Groups: None

Hi, 

I have a question, please help me. 

I revised durations in a schedule at P6 regardless of remaining units and remaining duration and submitted to HOD. 

The original budget available and duration type already defined by previous planner is fixed duration & units. 

The client asked to revise the budget and add the revised budget in P6 and then from P6 take the weekly planned budget. 

How can I revise the budget unit without changing the duration and date?

If I add the remaining units, the remaingin duration will change, so current completion date also will change. 

Please support me how to revise the budget units without affecting claimed completion dates and how to extract weekly budget unit from p6, same what we defined in excel in terms of weekly man-hour histogram????

Replies

Zoltan Palffy
User offline. Last seen 29 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

just filter by wbs and on the left use the + and - to roll up and to unroll the procurment activities also in the gropuing select show grand totals

Ali Reza
User offline. Last seen 6 years 34 weeks ago. Offline
Joined: 15 Mar 2017
Posts: 18
Groups: None

Hi, 

It is requested to show only procurement activities in P6 and all other ativities should be shown in summary level (wbs level). 

I filtered but summary of other activities are shown without date and without gantt chart bar.

Please help me in this case.  

Zoltan Palffy
User offline. Last seen 29 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

filter for ALL activities add a column look under the General Category and bring activity TYPE to the right

on the first activity at the top in the activity type column change it to fixed duration and units/time

now do a fill down in that column

now go to the Projects directory

make sure that your project is highlighted

click the defaults tab and select fixed duration and units/time

done

Ali Reza
User offline. Last seen 6 years 34 weeks ago. Offline
Joined: 15 Mar 2017
Posts: 18
Groups: None

Hi, 

Is any body can explain me about activity code and how to define new project activity codes? 

I want to define activity codes to filter easily accordingly. 

Ali Reza
User offline. Last seen 6 years 34 weeks ago. Offline
Joined: 15 Mar 2017
Posts: 18
Groups: None

Hi, 

How to make Duration % complete equal to physical % complete in P6?

Then, whenever we enter physical % complete manually, the duration % complete also updated same. 

Ali Reza
User offline. Last seen 6 years 34 weeks ago. Offline
Joined: 15 Mar 2017
Posts: 18
Groups: None

Thank you very much. 

I got it. 

Frank Douglas
User offline. Last seen 7 years 22 weeks ago. Offline
Joined: 13 May 2017
Posts: 2
Groups: None

I have no idea of it.

Zoltan Palffy
User offline. Last seen 29 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

change your duration tyeps to fixed duration & units/time 

Ali Reza
User offline. Last seen 6 years 34 weeks ago. Offline
Joined: 15 Mar 2017
Posts: 18
Groups: None

THANK YOU FOR YOUR ANSWERS. 

I HAVE ANOTHER QUESTION IN P6?

I added I added remaining unit for an activity, after re-scheduling the start & finish date will change without respecting to predessor. When I remove the remaining unit, It follows the relationship. 

Could you tell me how to avoid changing of dates in this situation?

Ali Reza
User offline. Last seen 6 years 34 weeks ago. Offline
Joined: 15 Mar 2017
Posts: 18
Groups: None

THANK YOU FOR YOUR ANSWERS. 

I HAVE ANOTHER QUESTION IN P6?

I added I added remaining unit for an activity, after re-scheduling the start & finish date will change without respecting to predessor. When I remove the remaining unit, It follows the relationship. 

Could you tell me how to avoid changing of dates in this situation?

Zoltan Palffy
User offline. Last seen 29 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

got to tools Global change and add a new global change

where  physical percent complete is greater than 0

then duration % complete  = physical % complete

then execute the global change press change

then committ chnages

do this afret each update after inputting ALL physical % completes

and before you calculate the schedule

 

 

Ali Reza
User offline. Last seen 6 years 34 weeks ago. Offline
Joined: 15 Mar 2017
Posts: 18
Groups: None

Hi to every body, 

When % complete type is physical, how the remaing will be calculated by P6?

Remaining duration I mean after changing of data date and  rescheduling???

Zulham Julio
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 16 Mar 2017
Posts: 2
Groups: None

excuse me sir, i,m newbie in this forum. how can i post a question in this forum? thank you

Zoltan Palffy
User offline. Last seen 29 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

change the duration type to fixed duration & units/time for all activities you can add that column duration type then do 1 then do a fill down