Recently moved to high level planning in Months & Quarter duration. Scary as I have come from Hourly Planning!!

I remember from P3 traning years ago that you can create a Global Change, probably with a Text Field Column to show Days into Months? Something like :

Original Duration / 30 = No of Months

 

Can someone tell me the Global Change Data should run in P6 please?

 

Thanks

 

Laura

A
Aldrin Morallos 👤 Member for 15 years

Hi Laura,

 

Try to provide separate 2 Text Column outside or beside OD column containing "Days" copied from OD & "Months" from there you formulate it using Global Change from Original Duration/30 and you'll see the result.

 

OD- Original Duration.

 

Thanks.

L
Laura Vass 👤 Member for 14 years 1 month

Thanks Raymund for your amazingly quick response.

I did do that one too.

You think away to show 2 columns? Months & Days?

R
Raymund de Laza 👤 Member for 16 years 7 months

Laura,

Global Change is not needed to show durations into Months.

Go to User Preferences... Time Units... Durations Format.. set Unit of Time to Months

 

Hope this will help.

 

Forum Sponsor

Top Posters

Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts