Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to see all Calnedars used in schedule

2 replies [Last post]
David Ball
User offline. Last seen 12 years 12 weeks ago. Offline
Joined: 26 Jan 2012
Posts: 10
Groups: None

Hi,

 

I am using P6 and would like to find a way that I can see all Calendars used in a schedule without having to scroll through every activity.

Is there a quick and easy way to see what Calendars are used in the schedule?

 

Thanks very much

DFB

Replies

Gary Whitehead
User offline. Last seen 5 years 25 weeks ago. Offline

David,

 

The easiest way is to go to View > Group and Sort > Group by Calendar, then colapse the groups. (right click on the spreadhseet, and select "Collapse All")

 

Might be worth inserting the "Activity Count" column, so you can see how popular each calendar is

 

Cheers,

 

G

Mike Testro
User offline. Last seen 1 day 14 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi David

Surely there is a column that will show the calendar attached to the task.

There is in every other software that I know.

Best regards

Mike Testro