Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Compare the progress vs baseline based on Duration concept in P6 as in P3

No replies
Ayman Eleish
User offline. Last seen 12 years 21 weeks ago. Offline
Joined: 28 Dec 2010
Posts: 48
Groups: None

Dear All,

How can I compare the progress vs baselinein P6 based on the duration concept as we used to do in P3.

In other words to calculate and rolling up the % progress based on the summation of executed durations divided by the summation of total durations .

Thanks and Regards,