Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Baseline has a baseline??

1 reply [Last post]
Natalie Wann
User offline. Last seen 12 years 46 weeks ago. Offline
Joined: 31 Jan 2012
Posts: 3
Groups: None

It seems as though my baseline project has a 'memory' and is storing dates (which are visible when showing BL columns and bars) yet there is no 'secondary baseline' attached...?

 

Background:

I was asked to rebaseline the current as-built programme due to changes.

I took the as-built programme (1) and made a copy (2) and extended dates so as to reflect changes in project. I then made a copy of these new dates (3) moved the data date and progressed activities and this became my new as-built programme. I attached (2) as the baseline to (3)

 

However when I come to running planned value numbers from the new baseline the data was incorrect in 2 ways:

- If an activity started 3 months ago but has only 5% of units earned I would expect the remaining 95% of budgeted units to spread from data date to the finish date. What is actually happening is that the programme is linear spreading the units from start date, week by week, so that even though it reads 5% it is actually planning to be around around 70% by data date...?

- Even though the finish date on an activity date is 30 March, the planned resource is stopping at 05 March. On further investigation it seems the baseline 'has its own baseline', even though this should be impossible, which has a finish date of 5 march and this is why the resources are stopping at this date. However I am completely unable to 'clear the memory'

 

Any advice would be very helpful!!!!

 

Thanks

Replies

Ronald Winter
User offline. Last seen 3 years 42 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None

Natalie,

If no P6 Baseline is set for the current schedule, P6 will display the Planned Dates from the current schedule when you ask to see the baseline.  Good Luck!