Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Assigning Updated Schedule (Has actuals) as Baseline

1 reply [Last post]
Asokan Ramamoorthy
User offline. Last seen 4 years 24 weeks ago. Offline
Joined: 1 Apr 2012
Posts: 11

Dears,

I have a issue while assigning the current schedule as baseline which has actuals already.

I have already changed the Planned Start=Start and Planned Finish=Finish.It works fine for Non started and Completed Activities.

But for all in progress activities i have an issue.Schedule % is not matching with the performance %. Could any one suggest solution on this regards please.

 

Not Activity % completion type is :Physical % Completion

Replies

Zoltan Palffy
User offline. Last seen 16 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

run a global change 

where physical % complete is greather than 0

then duration % complete = physcial % complete