Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Setting-Baseline that has Actuals and Constraints in P6

16 replies [Last post]
Anoon Iimos
User offline. Last seen 2 years 45 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Dear Planners,

I don’t really know if i’m doing this right, but I want to know the possibilities if I set a baseline that has actuals and constraints (inavoidable due to Engineering and Procurement).

1. Can I set a Baseline Schedule in P6 that has actuals and constraints? (I believe I can, but what would be the effect?); i.e. in Timesheets and time schedule?

2. Can it be justifiable setting a Baseline that has actuals and constraints? How?

Replies

Raymund de Laza
User offline. Last seen 1 day 14 hours ago. Offline
Joined: 22 Nov 2009
Posts: 762

Nith,

Restore your PB, open it, and execute Global change to make the Planned Dates = Current Dates.

Re attach PB into CP, assign again as PB.

Nithin Shetty
User offline. Last seen 7 years 30 weeks ago. Offline
Joined: 31 Aug 2004
Posts: 34
Groups: None

Hi Experts,

I have a difficulty here. I hope I get a good solution from you.

I have assigned a partially updated program as a Baseline (Project Baseline) (Say PB) to my current program (Say CP). Now I want to compare my current program (CP) to mentioned Baseline program (PB).  

I followed the usual steps. In the Bars template, I have selected 'Project Baseline Bar', 'Actual Bar', 'Remain Bar' etc.

But the display of 'BL project start' & 'BL project finish' shows Planned dates of PB instead of Actual Dates of PB. How can I fix this?

Really appreciate your help.

Kind Regards,

Nith

 

 

Nithin Shetty
User offline. Last seen 7 years 30 weeks ago. Offline
Joined: 31 Aug 2004
Posts: 34
Groups: None

Hi Experts,

I have a difficulty here. I hope I get a good solution from you.

I have assigned a partially updated program as a Baseline (Project Baseline) (Say PB) to my current program (Say CP). Now I want to compare my current program (CP) to mentioned Baseline program (PB).  

I followed the usual steps. In the Bars template, I have selected 'Project Baseline Bar', 'Actual Bar', 'Remain Bar' etc.

But the display of 'BL project start' & 'BL project finish' shows Planned dates of PB instead of Actual Dates of PB. How can I fix this?

Really appreciate your help.

Kind Regards,

Nith

 

 

R. Catalan
User offline. Last seen 12 years 39 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 314
Groups: None
Anoon,

I missed to read the current year for the thread.

Thanks anyway!

R. Catalan
Anoon Iimos
User offline. Last seen 2 years 45 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
R. Catalan,

Where did you find this thread? I even forgot that I started this one, thanks for digging anyway.

For now, I have no idea what happened then, or they had arrived into conclusion (I supposed they had).

Yes, I believe that constraints and actuals are things that you cannot avoid when setting-up a baseline, especially for EPC projects.

cheers
R. Catalan
User offline. Last seen 12 years 39 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 314
Groups: None
Hi Anoon,

Yes it is ideal for a baseline with no actuals, but I don’t think there’s a problem in keeping the actuals and constraints once you assign it as a baseline.

In fact in P6, you can’t only compare your current programme to the original baseline (BL for delay analysis), but also you can compare it with last week’s update (BL1 - slippage analysis).

I hope this will help you in concluding this thread.

Best regards,

R. Catalan
Anoon Iimos
User offline. Last seen 2 years 45 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
just read aacei’s RP for forensic schedule analysis (but i’m not sure if I understand it) and found an item: "De-statusing a Progressed Schedule to create a Baseline";

Say for example, you got a Schedule which is continuously updated (i.e. daily) but never Baselined and when the time comes that everybody is looking for a Baseline, you de-status it and forgot to have back-up, (i.e. you got around 5,000 activities, some of which has constraints - which happened actually), will the next update be valid?

apologies in advance
Anoon Iimos
User offline. Last seen 2 years 45 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Dear All,

At the moment, I personally believe that no one is really well versed in P6 (for it is not even a one year old program); and i also believed that it was programmed to produce precise output, in other words, garbage in - garbage out; however, Planning which evolved from the word uncertainties, cannot be certain unless it happened (meaning - past, which has actuals!).

For me, having constraints and actuals for a baseline program cannot be avoided especially if the works include Engineering and Procurement.

My concern is, the mindset of the Project Team, and to study a program without enough knowledge and experience is time consuming.

I just want to finish the Baseline Program, before the project ends!
A D
User offline. Last seen 4 years 2 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Just a quickie Anoon,

What u normally do in re-baselining the program? Are there any actuals in re-baseline program.

if ur answer is yes, then it is evident that we can use actuals in baseline program as well.

One more problem without the actuals in these type of programs is that then there will be lot of open-end activities in the program as the predecessor (having actual date) are not being entered.

Cheers,

Ravi
Johny Kesserwany
User offline. Last seen 7 years 44 weeks ago. Offline
Joined: 18 Sep 2007
Posts: 118
Hi,
the ’’AACE international Recommended practice’’ recommends that the Baseline schedules should be relatively free of imposed or “mechanical” constraints...

’relatively’ is very subjective!!!
Having up to now arround 3000 activities either constrainted or having actual dates, my advise would be have a talk with whom it may concern in the Acceptance of the baseline schedule to have his feedback on the subject... It will be a lost of time and energy to revise all these activities if the baseline is rejected....

Regards
JK
Dieter Wambach
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi
By internal calculation I meant scheduling, which is to calculate an algorithm. How precise this calculation will be, depends on the database’s parameters not on your preferences.
I you’ll create a baseline (by maintain bl) this is a complete copy of your project.
Regards
Dieter
Anoon Iimos
User offline. Last seen 2 years 45 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Hi Dieter,

What do you mean by internal calculation? I’m not really well versed in P6. I believe I cannot hide the settings or columns (even if I do, it is still there). I believe P6 uses calendars and timeperiod settings, whenever there are actuals, then the program will read it.

I am just trying to set-up a baseline (I supposed to be ideal), but I realized that there’s no such thing!
Dieter Wambach
User offline. Last seen 7 years 31 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi
Internal calculation does not depend on your user preferences, it depends on your data-base’s settings how many digits behind decimal point will be calculated. But in your preferences you can decide if you want to show the minutes to outside.
Regards
Dieter
Anoon Iimos
User offline. Last seen 2 years 45 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Thanks for the reply Mark, I’m setting up a Baseline Program (a new one), it is a Design and Build Project (EPC). The thing is, there are constraints that I have to consider as well as actual dates (which I supposed cannot be neglected in the program), I have around 3,000 activities at the moment, but I haven’t completed the program yet (there are still a lot of details to be considered - which I haven’t got yet).

P6, I supposed is calculating on hours (as planning unit); I don’t have a problem considering a baseline with constraints and/or actuals, my concern is, when I present it to the approver, I know that they’ll be asking about the set-up (i.e. start of a certain activity - please note, in terms of hours and minutes!). When you run the schedule in P6, I believe it calculates to minutes depending on your timeperiod settings (Admin preference and User preference), this is where the actuals and constraints will affect. i.e. Activities will not start exactly at 8:00 am and ends @ 5:00 pm (for an example).If we are going to use Timesheets...I don’t know.

I hope I made myself clear.

Mark Chapman
User offline. Last seen 8 years 41 weeks ago. Offline
Joined: 18 May 2006
Posts: 183
Groups: None
Anoon,

I don’t have P6 but P5. I can tell you that ALL baselines SHOULD have constraints -its not a necessity but you aren’t planning if you don’t have constraints in your plan.

As for actuals, I haven’t tried this in P3 but I would expect there not to be a problem. Are you taking a new baseline or copying the current programme to an old baseline? If its the latter I am unsure. I guess you should just try it and see but take backups first.

I hope this helps,

Mark
Anoon Iimos
User offline. Last seen 2 years 45 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
it’s quite hard to get a reply either, my concern is that the approver of the Baseline is very meticulous that he wanted to see the Hours and Minutes in the Program (but I supposed that he doesn’t have any clue of what he is looking after);

somehow, i believe that an ideal Baseline has no constraints or actuals (but in real world, things are different)

any ideas?