Update Data date 1st time....

4 replies [Last post]
Jenny Ingco
User offline. Last seen 2 years 45 weeks ago. Offline
Joined: 9 Jan 2012
Posts: 116

Dear All....

I have a little problem with updating my schedule data date,, I start load the actual start date to my current schedule for some activities and then update the data data to the current date I moved it 4 monthes, the problem now I got very high -ve TF... So, I am very thankfull for any advises how I can fix that?

Thank you all..

Replies

Frederic Fasquelle
User offline. Last seen 1 year 27 weeks ago. Offline
Joined: 16 Mar 2006
Posts: 61

Negative float can either come incorrect finish date of your project (as explained by Hilal), either you have put constarint.

Primary constraints like Mandatory start/finish, "Start on", "Finish on" are deleting your float.

It means that even if you have margin, by applying these constraints, P6 launch calculation considering them as 0 float. Any delay will thus generate negative float,

Frederic

Jenny Ingco
User offline. Last seen 2 years 45 weeks ago. Offline
Joined: 9 Jan 2012
Posts: 116

Dear All,

Thank you very much for your great help. I did try to change the finish date of the project it's work ok for overall TF but still have -ve values for some WBS's and I don't want to change the duration also I am talking about 4000 activities. I got TF=-170 so how I can avoid that? Also, I need to know if that commen issue if I show the owner my current schedule with -ve TF?

Thank you again,,

Hlamalani Baloyi
User offline. Last seen 12 years 7 weeks ago. Offline
Joined: 20 Jan 2012
Posts: 18
Groups: None

can you really avoid negative float? i dont think you can, its a matter of a program telling you where you will not meet your finish date,

Hilal Hallani
User offline. Last seen 12 years 22 weeks ago. Offline
Joined: 3 Nov 2011
Posts: 16
Groups: GPC Qatar

Hello Hani,

I had this same problem when developing a programme. I had negative floats because my finish date in the programme did not match the "must finish by" date in the project details tab. When I changed the "must finish by" date in the project details tab to match the finish date in the actual programme, my negative floats changed to zero.

Regards

Hilal Hallani