to run that global change that you wanted 1st creat a udf call it matper is under Enterprise User Defined fields make that data type a number
then create a new global change where duration % complete is greater than 0
the matper = duration % complete
now run another global change make sure that in the global change that at the top under the selet subject area that you change this to activity resource assignments
the global change would be
where Resource Type equals Material
then Actual cost = matper * Budgeted Cost
Member for
6 years 4 months
Member for6 years4 months
Submitted by Rahul Prasad on Tue, 2019-06-18 14:59
You need to set all material costs to £1 per unit. Then budgeted quantity equals budgeted cost. You can then tick the calculate costs from units box again and normal service is resumed. If you want the real quantities, you will need to add a udf.
Member for
16 years 3 monthsto run that global change
to run that global change that you wanted 1st creat a udf call it matper is under Enterprise User Defined fields make that data type a number
then create a new global change where duration % complete is greater than 0
the matper = duration % complete
now run another global change make sure that in the global change that at the top under the selet subject area that you change this to activity resource assignments
the global change would be
where Resource Type equals Material
then Actual cost = matper * Budgeted Cost
Member for
6 years 4 monthsHi,I also ran into a similar
Hi,
I also ran into a similar problem in my programme in P6, v16.2.
The solution that worked for me is as follows:
1. Proceed to the Projects - Resources Setting Tab
2. And under the Assignment Defaults; have the "Drive activity dates by default checked".
This should enable the Actual Cost of the Activity to be calculated from the % Completed.
Member for
21 yearsVery interesting. You need
Very interesting.
You need to set all material costs to £1 per unit. Then budgeted quantity equals budgeted cost. You can then tick the calculate costs from units box again and normal service is resumed. If you want the real quantities, you will need to add a udf.
Have fun!