Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Copying a Project from one EPS to another.

4 replies [Last post]
Brent Gaspard
User offline. Last seen 12 years 37 weeks ago. Offline
Joined: 18 Jan 2012
Posts: 2

I have a project with 19,000 activities. When I copy this Project from one EPS Node to another, only some of the activities & only some of the activity codes copy over. I have tried the regular copy & paste at the Project Level, I have Exported it & the Imported it back in, I have copied it at a WBS Level. None of these have worked. What am I doing wrong?

Replies

Anning Sofi
User offline. Last seen 6 years 21 weeks ago. Offline
Joined: 22 Jan 2012
Posts: 89
Groups: None

Importing only the codes would not solve  Brents problem because his issue is not only codes missing but also some activities are not copied.

I can guess Brent, that when you were exporting and importing the files, if you happen to click on the mouse or work on other applications during the process, P6 will tend to "freeze or hang". After some time, you see the message, import successful, but after checking the import file, some files and relationships or codes are missing. These can happen to your project which has 19000 activities, cause we experience the same issue in our project of almost similar size of activities.

Our solution was to export/ import and leave it until P6 completes the process.


 

Kashif Khan
User offline. Last seen 11 years 1 week ago. Offline
Joined: 16 Nov 2011
Posts: 46
Groups: None

Please check the filter, becuase sometimes auto filter starts in P6 when ever you copy n paste or alter the WBS of project.

Raymund de Laza
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 22 Nov 2009
Posts: 762

Hi,

I had experienced the same problem.

What I did was to export the activity codes of the original project then import it in the new project and it works.

Hope this wil help.

Anning Sofi
User offline. Last seen 6 years 21 weeks ago. Offline
Joined: 22 Jan 2012
Posts: 89
Groups: None

There is a limitation on how much data P6 can copy from one whole project to a new copy. Obviously, with 19,0000 activities,with an estimate of 40,000 relationships and cost loading/resource load, the file size would be around 35+MB.

I am sure to reduce clipboard memory size in the file, you may have tried to copy data by opening two files (the file to be copied, and the new file copy) at the same time, copied by WBS or code group and l lose some of the relationships or other data.

Even if you increase your hardware RAM to 4MB, you will still face the same copy issues.

The better option you have  available is to export the file, and reimport it; although it will take around 30-40 minutes to complete the process.