Resource Working Alternate Months How to Model this in Primavera

1 reply [Last post]
Muhammad Zeeshan ...
User offline. Last seen 30 weeks 33 min ago. Offline
Joined: 12 Mar 2008
Posts: 45
Groups: None

Oh HI Guys

I hope you are doing well.

One my resource is working alternatively on my project how do i model this resource hours on my plan

Package A 

Resource X

working 2 days  Jan , Mar , May, July , Sept , Nov.

I have used suspend activitu but it does not work

Any other suggestions will be appreciated  

 

Replies

kumar s
User offline. Last seen 9 years 9 weeks ago. Offline
Joined: 26 Jan 2010
Posts: 159

Dear,

I think the easiest way is to create a calendar based on your working criteria that is alternate months and 2 days working.

 

Cheers,