Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Cost Issue when importing contractor schedule into existing project in P6v7.

1 reply [Last post]
Ryan Rowland
User offline. Last seen 8 years 33 weeks ago. Offline
Joined: 15 Feb 2011
Posts: 11
Groups: None

Typically, when reviewing contractor schedule, I import their newly submitted file into the existing file that we maintain for that project, but when doing so, if the contractor has made any changes to the expenses during the update, they seem to add on top of the current expenses for example, Total Budgeted Cost originally is $15,000 , but the contractor moves expenses around between activities (eg. moves $500 to another activity). When schedule is imported, the new Total Budgeted Cost shows $15,500, even though it shows $15,000 (The correct amount) if you import and open the file as a seperate project. What can I do to prevent this from happening when I import the schedule into the existing schedule file?

Replies

Arnold Puy
User offline. Last seen 9 years 42 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147

Hi Ryan,

During importing make sure that the "Update Project Options",  Select Add --> Rename Layout Name for future use, double click the No, to become "Yes" and select Modify --> Modify Import Configuration under Data Type: Project --> Project Expenses, change the "Update Existing" to "Keep Existing".

Best regards,

Arnold