Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Showing Early and Late Cost curves in P6

2 replies [Last post]
Sebastian DiBlasi
User offline. Last seen 10 years 7 weeks ago. Offline
Joined: 18 Apr 2011
Posts: 13
Groups: None

I have a baseline cost loaded schedule that I want to see cost curve based upon the early and late dates. The profile can generate early, but not late. Is there a way to do this? Also is there a way to show in tabular form the cost by early and late dates?

Replies

Khaja Sharief
User offline. Last seen 10 years 40 weeks ago. Offline
Joined: 9 Sep 2008
Posts: 44

Select activity usage/resource usage profile. Now right click on the graph and select activity usage profile options/ resource usage profile options.  Under bars/curves area, select the remaining early or remaining late. You can play around this, you can veiw this in terms of units as well as costs. 

Karim Ragab
User offline. Last seen 9 years 5 weeks ago. Offline
Joined: 6 Dec 2011
Posts: 7

Me too