Hi All,
I'm currently doing Delay Analysis using P6 software and having issues with the functions/buttons in P6. Ive been using P6 only for some months but i've grown for years in planning and schedulling using P3 software.
To simply illustrate my problem, i would lay some parameters.
1. Programme A (baseline programme)
2. Programme B (as-built programme / updated programme)
3. Programme C (Impacted as Planned Programme, a consolidation of infos from Programme A and B)
4. Programme A, B and C are typical Programmes with typicall Activity IDs. Activities are: A1, A2, upto A100
Now, using P6 software, my problem is I wanna Extract informations (i.e. AS, AF, % Complete) from Programme B's A10 to A20 ONLY and export these Informations to Programme A to create Programme C.
So in overview, Programme C is the consolidated informations of Programme A's activities A1 to A9, A21 to A100 AND Programme B's activites A10 to A20. This is my method in order for me to create "Impacted As-Planned" Analysis, extracting the Delay Event Activities (which in this illustration is the A10 to A20 activities) and Impact the these activities (A10 to A20) to Programme A (considering that AS and AF are the same to as-planned/baseline of the activities A1 to A9, A21 to A100) in order to determine the Impact of the Delay Event to the over-all Project duration.
I hope my illustration to my problem can be well understood.
This procedure of exporting informations from one programme to typicall programme is PEANUTS for me in P3 software. In P3 software, i will just use the "Send Mail" and "Recieve Mail" functions. In P6 software, I have no idea how to do these methods since the "Send Mail" and "Recieve Mail" functions have been removed in P6.
I'll be glad to hear from you guys and thanks in advance..
Replies