P6 Calendar - modify work hours

2 replies [Last post]
Ife Olyke
User offline. Last seen 10 years 5 weeks ago. Offline
Joined: 6 Feb 2007
Posts: 147

Hi Planners,

I have an activity (let’s say its activity ‘A’) within my P6 plan that will take 6 hours to complete and has a fixed start date and time. In carrying out this task, no other activity can be progressed. I need to make this visible in the P6 plan by setting the work hours for activity ‘A’ on the day as ‘Nonwork ‘. Alternatively, I could set the whole day, but that will portray a false impact on the schedule duration.

Who has got an idea? Thanks

 

olyke

Replies

Ife Olyke
User offline. Last seen 10 years 5 weeks ago. Offline
Joined: 6 Feb 2007
Posts: 147

Please ignore post, problem solved.

Gary Whitehead
User offline. Last seen 5 years 6 weeks ago. Offline

Could you not just make Activity A a predecessor of all other activities?

If you try and do it with calendars, what happens if Activity A is delayed?