P6V7 levels resource actual units

1 reply [Last post]
Alexandre Faulx-B...
User offline. Last seen 2 years 30 weeks ago. Offline
Joined: 20 Jan 2003
Posts: 1355
Hello planners, on Activity A, Original Duration 5 days, Resource 1 is working 8 hour/day Activity Actual Start is Monday and Actual Duration 2 days Update Progress on Tuesday night shows Resource 1 Actual Units = 16h, 8 on Monday and 8 on Tuesday On Wednesday night, I schedule the project to show that there was no work at all on Activity A on Wednesday; on the Activity Usage Spreadsheet, P6 shows that Resource 1 worked 5,33 hours per day during 3 days, when I want to read 8 hours per day during 2 days and 0 on Wednesday I cannot find where the setup is Please somebody help! All the best, Alexandre

Replies

Raymund de Laza
User offline. Last seen 3 weeks 6 days ago. Offline
Joined: 22 Nov 2009
Posts: 762

Hi,

That happens because the default resource curve is linear or rectangular.

My advise is use a modified resource curve to control what you wish to define.

Hope this will help.

 

Regards,

 

Raymund