How to know target Percentage for the next week ?

2 replies [Last post]
Irfan Khan
User offline. Last seen 28 weeks 1 day ago. Offline
Joined: 19 Jul 2009
Posts: 138

Hi to all expertise,

I have updated my schedule now the over all progress is 12.67 % on data date 15-01-2011.
I want to know target percentage for next week of my each WBS as per assinged baseline..

how to show these percentage ?

please need help,,


thanks,,,,,
 

Replies

kumar s
User offline. Last seen 8 years 48 weeks ago. Offline
Joined: 26 Jan 2010
Posts: 159

Dear Irfan,

if you want  to know the target complete % for the next week then go to the projects window there in the dates tab change only the Data Date to the next week but do not schedule..

like this you can get the % complete for the future periods...

 

kumar s
User offline. Last seen 8 years 48 weeks ago. Offline
Joined: 26 Jan 2010
Posts: 159

Dear Irfan,

if you want  to know the target complete % for the next week then go to the projects window there in the dates tab change only the Data Date to the next week but do not schedule..