Earned Value - At Completion values with Current dates

Dear All,

In Admin Preferences , Earned value tab , we have 3 methods to choose earned value

1) Budget value with Planned dates.

2) Budget values with Current dates.

3) At completion value with current dates.

I have a clear idea the use of the first two. But i want somebody to explain what is use of having " At completion values with current dates to compute Earned value management.

Pls help.

 

regards,

 

Haresh Jayanth - PMP

Z
Zoltan Palffy 👤 Member for 16 years 11 months

the key wording here is the 1st word Budget of the 1st 2 options the 3rd option is AT completion which could be more or less than the budget.

D
Dinesh Kumar 👤 Member for 20 years 1 month

1) Budgeted value with planned dates

PV = budget value x time spread or budget value x cost spread

 2) Budgeted value with current dates

PV = budget x current elapsed duration / total duration with expected completion

3) At completion value with current dates

PV = EAC x current elapsed dur / total dur with expected completion

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts