Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Earned Value - At Completion values with Current dates

2 replies [Last post]
Haresh Jayanth
User offline. Last seen 6 years 30 weeks ago. Offline
Joined: 24 Aug 2006
Posts: 219

Dear All,

In Admin Preferences , Earned value tab , we have 3 methods to choose earned value

1) Budget value with Planned dates.

2) Budget values with Current dates.

3) At completion value with current dates.

I have a clear idea the use of the first two. But i want somebody to explain what is use of having " At completion values with current dates to compute Earned value management.

Pls help.

 

regards,

 

Haresh Jayanth - PMP

Replies

Zoltan Palffy
User offline. Last seen 25 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

the key wording here is the 1st word Budget of the 1st 2 options the 3rd option is AT completion which could be more or less than the budget.

Dinesh Kumar
User offline. Last seen 4 years 49 weeks ago. Offline
Joined: 8 May 2006
Posts: 29

1) Budgeted value with planned dates

PV = budget value x time spread or budget value x cost spread

 2) Budgeted value with current dates

PV = budget x current elapsed duration / total duration with expected completion

3) At completion value with current dates

PV = EAC x current elapsed dur / total dur with expected completion