COPY & MODIFY SCHEDULE

3 replies [Last post]
Shazia khan
User offline. Last seen 12 years 23 weeks ago. Offline
Joined: 21 Apr 2008
Posts: 139
HI-

I have a schedule which i want copy and modify for other project how i can perform the step.

i try to export it. then i try to import in diffrent EPS it was import in Diffrent EPS,

Please advise

Thanks & Regards

Replies

Shazia khan
User offline. Last seen 12 years 23 weeks ago. Offline
Joined: 21 Apr 2008
Posts: 139
Thanks so much for you advise,

i did the same and its worked fine.

Thanks so much for Advise and Best regards
Rodel Marasigan
User offline. Last seen 7 weeks 1 day ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Hi Shazia,
It is as simple as copy and paste then rename then start modifying as new Project. You can also export to XER and import to Methodology Management and use as a template or project fragment.
Samer Zawaydeh
User offline. Last seen 5 years 20 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Hi Shazia,

You can save it under a different name with the new project, and then modify it. That is easier.

With kind regards,

Samer