P6 - Setting Resource min/max limits

1 reply [Last post]
Vaughn Edwards
User offline. Last seen 10 years 28 weeks ago. Offline
Joined: 1 May 2008
Posts: 16
Wants to know how to set min/max limits on project resources.

Replies

Rodel Marasigan
User offline. Last seen 11 weeks 4 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Vaughn,
Enterprise-> Resources-> Unit & Price tab. If no record underneath click Add and enter Max unit/Time.