Relationship Lines

2 replies [Last post]
Sukumaran Subaram...
User offline. Last seen 9 years 10 weeks ago. Offline
Joined: 2 Mar 2005
Posts: 229
Groups: GPC Malaysia
Hi! Guys,

I need your assistance to change the relationship lines from Baseline to Current bar.

Earlier the relationship lines in my schedule are in correct order. Relationship lines were shown in Current bar. But somehow the relationship lines are now shown in Baseline bar.

Does anyone have idea how to change back the relationship lines from Baseline to Current bar.

TQ.

Replies

Sukumaran Subaram...
User offline. Last seen 9 years 10 weeks ago. Offline
Joined: 2 Mar 2005
Posts: 229
Groups: GPC Malaysia
Rodel,

Thanks for your assistance. Your input has solved the problem.

Sukumaran
Rodel Marasigan
User offline. Last seen 17 weeks 2 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Sukumaran,
You can control relationship line on Bar Format (View-> Bar). The first on top activated Bar is where the relationship lines follow. If you wanted to show relationship line on current bar then move up the current bar (remaining bar) and make sure it is activated or tick. You can move up any bar define and activated (tick) then the relationship line will follow which ever is on top or first.