Relationship lines
Forum Sponsor
Top Posters
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
Thank you all
Just worked out!!!!!!!
That was fantastic.
Keep it up.
Julius Achy
Hi Julius
this is caused by the sequence of the bars in the Bar-format window. Just put yr current bar up, so it is before yr baseline bar
Move the Baseline bar below the other bars in the bars form and this will put the relationships on the current schedule bars.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
www.eh.com.au