Setting timescale Gantt - P5

4 replies [Last post]
Conrad Cannella
User offline. Last seen 13 years 34 weeks ago. Offline
Joined: 28 Nov 2008
Posts: 17
How can i setting timescale gantt to be see number of the day of the week and not the name of the day of the week...Thanks

Replies

Conrad Cannella
User offline. Last seen 13 years 34 weeks ago. Offline
Joined: 28 Nov 2008
Posts: 17
Thanks a lot!
Rodel Marasigan
User offline. Last seen 15 weeks 12 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Conrad,
The only setting on Timescale that show day date is using Three line and select Day Shift as Date interval. The last line will be showing 0 if no nightshift calendar used.
Conrad Cannella
User offline. Last seen 13 years 34 weeks ago. Offline
Joined: 28 Nov 2008
Posts: 17
Thanks for the timely rispost.Molto bright as ever. But maybe I explained bad. I wanted to display the corresponding number of weekday and not a progressive. For example, in the year 2010 the first level, second level the months and third level the number of days of that from day 1 to day 30, one month from day 1 to 31, etc. ...
Thanks a lot
Rodel Marasigan
User offline. Last seen 15 weeks 12 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Conrad,
Right click on Gantt Chart area and select Timescale.
Tick Show Ordinal date and select the date interval you want to use and change the Start date to match number value you wanted to show. If you wanted to show both click Three Lines and you can select both.