Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P6 - calculate rem. units based on Activity % comp.

1 reply [Last post]
Abhijeet Ranadhir
User offline. Last seen 11 years 4 days ago. Offline
Joined: 29 Jun 2006
Posts: 26
Groups: None
I need help to calculate remaining Units on resources in P6 based on the activity % complete. I want to physically update % comp and accordingly want to cacluate the reaource actual and remaining based on the physical % comp. Will I be able to do this?

Replies

Rodel Marasigan
User offline. Last seen 8 weeks 6 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Abhijeet Ranadhir,
If your duration type is either Fixed Duration & Units or Fixed Duration & Unit/Time and Percent Complete type is Duration % then updating % complete will automatically update Actual & Remaining duration (synchronise update). If you are using Physical % for Percent Complete type then everything is manual input.