Case-
We have a budget base WBS in SAP for like this
Infra
Plant civil Bldgs
Non Plant civil Bldgs
Plant & Machinary
Others
We Follow the WBS in Primavera like this
Engineering
Tendering & Procurement
Delivery
Construction
L-2Civil
L-2Mech
Commissioning
Now we will keep the Primavera WBS for all level is as same as SAP WBS and under these the all detail activities will be listed down. But for the Schedule reporting purpose , we will assign activity codes like , Engineering , T&P , Delivery, Construction , Comm. to view reporting like this ..
Problem starts when - Correlation of SAP progress with Schedule in Primevera .
If SAP says - Actual cost in civil is - 30 %
Will Primavera rollup & show the Civil progress 30% or near to it , based on the Activity code(Civil) assign to civil related activities in all project considering weightage will be at acitivity level , Will it rollup the progress based on acitivity code grouping .