Resource usage spreadsheet error

5 replies [Last post]
Lucas l
User offline. Last seen 14 years 15 weeks ago. Offline
Joined: 13 Mar 2010
Posts: 37
Groups: None
In resource usage spreadsheet, the total for my manhour doesn’t add up correctly.

I believe this has to do with the calender.

Can anyone guide me how to resolve this issue

For instance, 3+3 = 9.76

By multiplying 0.615, I can get the correct amt

Replies

Tony Marsh
User offline. Last seen 12 years 7 weeks ago. Offline
Joined: 3 Jan 2012
Posts: 5
Groups: None

Hi,

Did you ever get a resolution to this problem? i am experiencing the same issue with the total not calculating correctly.

Cheers

 

Tony

Tony Marsh
User offline. Last seen 12 years 7 weeks ago. Offline
Joined: 3 Jan 2012
Posts: 5
Groups: None

Hi,

Did you ever get a resolution to this problem? i am experiencing the same issue with the total not calculating correctly.

Cheers

 

Tony

Rodel Marasigan
User offline. Last seen 4 days 8 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Lucas,
Are we talking durations or labor units and non-labor units? There is no way calendar will affect resource unit or qty. Calendar and unit/time will affect durations but not resource.

Note: You cannot sum a combination of material qty, labor unit and non-labor unit on a summary band. It combine in a summary band it will display "---" but can sum per resource type.
Lucas l
User offline. Last seen 14 years 15 weeks ago. Offline
Joined: 13 Mar 2010
Posts: 37
Groups: None
Hi,

It’s not a decimal problem as it show 3.00+3.00=9.57

The correct total is 0.615 times the value and apply for all the total for manhr and non man hr. There are no mistake for material.


I guess it is either calender or time period mistake. As I have change the calender from a 24hr calender to a 13hr calender. I tried changing the setting many times but couldn’t resolve the issue
Rodel Marasigan
User offline. Last seen 4 days 8 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Lucas,
It’s nothing to do with your calendar. Your units may have decimal. Try to show the decimal so you know where the sum came from. Edit-> User Preferences-> Time Unit tab-> Unit of Time-> Decimals. Change the decimal to 2. Also check spreadsheet Option and culculate average maybe tick.