P6; Resource Usage Spreadsheet

2 replies [Last post]
Abeer Mahmoud
User offline. Last seen 8 years 23 weeks ago. Offline
Joined: 8 Jul 2008
Posts: 87
• During May:
1- available units (Resource limit per month) = 42hrs per day X 30d = 1260hrs
2- actual units = 500hrs
3- remaining units = 600
4- Required/downtime units = 1 - (2 + 3) = 1260 - (500 + 600) = -160hrs

• During June:
1- available units (Resource limit per month) = 42hrs per day X 30d = 1260hrs
2- actual units = 0hrs
3- remaining units = 1000hrs
4- Required/downtime units = 1 - (2 + 3) = 1260 - 1000 = 260hrs

• During July:
1- available units (Resource limit per month) = 42hrs per day X 30d = 1260hrs
2- actual units = 0hrs
3- remaining units = 0hrs
4- Required/downtime units = 1 - (2 + 3) = 1260 - 0 = 1260hrs

Regarding that I tried to spreadsheet fields’ customized options but I think I chose a wrong options so If any one have any idea via resource usage spreadsheet or any other report/way please feed me back with steps.

Regards,

Abeer

Replies

Mike Testro
User offline. Last seen 23 hours 59 min ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Abeer

I have moved this thread to the p6 forum - you will get a better response here.

Best regards

Mike Testro
Abeer Mahmoud
User offline. Last seen 8 years 23 weeks ago. Offline
Joined: 8 Jul 2008
Posts: 87
Dear All,

At P6, Kindly note that if I have a resource code R#1 limit is 42hrs per day this resource was assigned for many activities starting in Mar. and finished in Aug.

And I updated schedule in May 10, 2009

So I need a resource usage spreadsheet showing the following data:
• During May:
1- available units (Resource limit per month) = 42hrs per day X 30d = 1260hrs
2- actual units = 500hrs
3- remaining units = 600
4- Required/downtime units = 1 - (2 + 3) = 1260 - (500 + 600) = -160hrs

• During June:
1- available units (Resource limit per month) = 42hrs per day X 30d = 1260hrs
2- actual units = 0hrs
3- remaining units = 1000hrs
4- Required/downtime units = 1 - (2 + 3) = 1260 - 1000 = 260hrs

• During July:
1- available units (Resource limit per month) = 42hrs per day X 30d = 1260hrs
2- actual units = 0hrs
3- remaining units = 0hrs
4- Required/downtime units = 1 - (2 + 3) = 1260 - 0 = 1260hrs

Regarding that I tried to spreadsheet fields’ customized options but I think I chose a wrong options so If any one have any idea via resource usage spreadsheet or any other report/way please feed me back with steps.


Regards,

Abeer