How to show inactive period in an activity which is yet

1 reply [Last post]
Jiso Thomas
User offline. Last seen 11 years 8 weeks ago. Offline
Joined: 15 Mar 2008
Posts: 15
Gents,

We are looking for an option where we will be able to indicate an inactive period in an activity which is yet to start? For example :

Activity Start : 1-May-10
Activity Finish : 1-Sep-10
Data Date : 1-Apr-10
Inactive period required : 15-May-10 to 15-Jun-10

Can we get any help on this?

Replies

Rodel Marasigan
User offline. Last seen 6 weeks 5 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Jiso,
All you need is to assign calendar with inactive period as stated. The bar will still looked straight across from 1-May-10 to 1-Sep-10 but if you set the Bar Necking Settings to Calendar non working time then it will show inactive period.