P6.1 Assign resources fixed budget units problem

2 replies [Last post]
Abeer Mahmoud
User offline. Last seen 8 years 6 weeks ago. Offline
Joined: 8 Jul 2008
Posts: 87
Dear All,

Kindly note that I have a project with 500 activities and I assigned resources for it but I have a big problem:

I have resource R#1 18h/d and for example I assigned it to activity AB with budget unit = 100hrs this activity duration is 15days.

When I changed this duration to 18 days this budget units changed automatically to 120 hours which not correct/applicable at all I need to fix the budget unit to be 100hrs even I change the duration.

How can I do this by default way please by steps and kindly note that it is urgent?


Best Regards,

Abeer

Replies

Abeer Mahmoud
User offline. Last seen 8 years 6 weeks ago. Offline
Joined: 8 Jul 2008
Posts: 87
Thanks Ronald;
I selected Activity Duration Type (on the General Tab) to “Fixed Units” and it worked.

Best Regards,
Abeer
Ronald Winter
User offline. Last seen 3 years 19 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
In P6, the activity duration, resource quantity, and resource rate are always balanced. To fix the activity duration and the quantity (budget), then it is necessary to set Activity Duration Type (on the General Tab) to “Fixed Duration & Units” and let the rate change as needed. Good luck!