P6.1 Assign resources fixed budget units problem

A
Abeer Mahmoud 👤 Member for 18 years

Thanks Ronald;

I selected Activity Duration Type (on the General Tab) to “Fixed Units” and it worked.



Best Regards,

Abeer

R
Ronald Winter 👤 Member for 23 years 6 months

In P6, the activity duration, resource quantity, and resource rate are always balanced. To fix the activity duration and the quantity (budget), then it is necessary to set Activity Duration Type (on the General Tab) to “Fixed Duration & Units” and let the rate change as needed. Good luck!

Featured Partner

Top Posters

Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts
James Williams
75 posts
xerxes
0 posts
edwin
0 posts
jhalluk69
0 posts