WBS- SUMMARY DURATION

7 replies [Last post]
Alaa Al haj
User offline. Last seen 7 years 42 weeks ago. Offline
Joined: 7 Nov 2007
Posts: 79
HI
EID MUBARAK TO ALL
does anybody know how primavera 6 calculate original duration for WBS- level when organizing activities by WBS
cause i have 12 W/ H calendar but primavera consider as 20 hours when calculating duration for wbs level
i don’t know why

yours
Alaa

Replies

Alaa Al haj
User offline. Last seen 7 years 42 weeks ago. Offline
Joined: 7 Nov 2007
Posts: 79

Thanks All
i change the default Global Calendar to match the project Calendar
and now it is ok
i don’t know what will we do without the best planner around the world on this Forum

thanks again
we should be proud of this Forum


yours
Alaa
Arnold Puy
User offline. Last seen 9 years 43 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Neil,

You are right..

It’s okey..

Regards,

Arnold
Neal Walsh
User offline. Last seen 4 years 7 weeks ago. Offline
Joined: 16 Sep 2007
Posts: 49
*Arnold

Sorry Arnie! :-)

Neal Walsh
User offline. Last seen 4 years 7 weeks ago. Offline
Joined: 16 Sep 2007
Posts: 49
Alaa,

This has always been an issue with P6, upto 6.2, and as Arniold states, v7 has its own time periods to correct this problem.
However, on versions prior to this, set your durations to hours and the issue will be resolved.

Regards,

Walshy
Arnold Puy
User offline. Last seen 9 years 43 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Alaa,

Try to use WBS Summary as activity type for each WBS level or to the highest level.

With P6 v7, each calendar has its own "Time Periods" so you don’t have to worry.

Regards,

Arnold
A D
User offline. Last seen 4 years 2 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
at summary level, P6 uses global calendat to calculate duration.

Global calendar and project calendar need to be same to show matching figures
Anoon Iimos
User offline. Last seen 2 years 45 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
please check your global calendar