Primavera v 6.2 to 8.2 - WBS Summary Duration using Global Calender

1 reply [Last post]
Melvin Perez
User offline. Last seen 10 years 46 weeks ago. Offline
Joined: 25 Sep 2008
Posts: 3
Groups: None

Hi to all experts,

 

After migrated form Primavera v 6.2 to 8.2 i have problem wbs summary duration. I import file to latest version but when I choose global calendar default (ex 7 days or 6 days/week calander) wbs summary duration not changing in R8.2 but in V6.2 it works.

Kindly provide me asisstance to anyone know solution of this problem?

 

Thanks in advance.......

Replies

Ferdinand U.
User offline. Last seen 6 years 46 weeks ago. Offline
Joined: 19 Jul 2007
Posts: 142

Hi Melvin, Latest P6 based the summary (if calendar is not the same for all activities under that WBS) from Project Calendar not from Default calendar. Here's from P6 Help, "if all the activities are not using the same calendar, then the values are calculated as follows:

  • If all the activities under the group band are in the same project, then rolled up duration and unit values are calculated using the project’s default calendar.
  • If all activities under the group band do not belong to the same project, then rolled up duration and unit values are calculated using the default global calendar."