Reset the progress

3 replies [Last post]
Salar Al Zubaidi
User offline. Last seen 2 years 20 weeks ago. Offline
Joined: 10 Apr 2007
Posts: 30
Groups: None
Gents,

Can someone help me with this issue please, as I have converted a programme from P3 to P6, the programme is been updated and had a schedule completion % and Actual days, I am trying to return it back to the un progressed programme (Virgin programme but not the baseline), can someone tell me the steps in details like for instance what I need to write in the WHERE area and the THEN area to sort this out.

Regards,

Salar

Replies

David Scott
User offline. Last seen 13 years 46 weeks ago. Offline
Joined: 5 Nov 2010
Posts: 2
Groups: None

Thanks Muhammad,

I need to replicate last years outage schedule exactly for this year, then make some modifications from lessons learnt.

I'll have a little mess about with global change, as I need to use the actual durations recorded from last year as the new original durations for this year. 

Regards

Dave

Salar Al Zubaidi
User offline. Last seen 2 years 20 weeks ago. Offline
Joined: 10 Apr 2007
Posts: 30
Groups: None
Thanks Muhammad i will try it ! my mail address is

salar_alzubadi@yah.....com

Regards,

Salar
muhammad anwar
User offline. Last seen 4 years 11 weeks ago. Offline
Joined: 5 Feb 2007
Posts: 46
Groups: TILOS
Salar,

In order to deprogress a project four things you need to do

1 - Pull the data date to start of the project

2- Set the Actual labour and nonlabour units to 0 by fill down method ( display columns, set first to zero and use fill down for the rest)

3- Set status of activities from progress or completed to ’Not started’ by global change

4- Set Remaining duration ’RD’ to Origianal duration by Global change


Then you almost done
For 3 - Global change

if All of the following
where Activity status is not equal Not started

Then
Activity status = Not started

and hit the change button

For 4 - Global change

Then Remaining Duration = Original Duration

and hit the change button.

Hope this will help