Global Change - Erase the budgeted labor units

3 replies [Last post]
Izam Zakaria
User offline. Last seen 7 years 32 weeks ago. Offline
Joined: 28 May 2006
Posts: 221
Hye everybody,


Is it anyone know how to eliminate all existing "BLU" via global change.

I can do that in P3 but not in P6

Thanks in advance guys.........

Replies

Izam Zakaria
User offline. Last seen 7 years 32 weeks ago. Offline
Joined: 28 May 2006
Posts: 221


oh guys...all of you are the man. Always there when I’m in trouble.

Cheer
R. Catalan
User offline. Last seen 12 years 20 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 314
Groups: None
Hi Izam,

If you want to remove all BLUs, follow Arnold’s advise but keep the "Where" statement blank.

Regards,
R. Catalan

Arnold Puy
User offline. Last seen 9 years 23 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Izam,

If you want to remove only the BLU and make it equal to zero then try this:

Select Subject Area = Activity Resource Assignments

Where
Resource ID Name "is under" Resource ID Value/Name

Then
Budgeted Labor Units " = " 0

However, if you want to delete the assignment then you don’t need to perform a global change.


Regards,