Budgeted Units were Multiplied by 8

4 replies [Last post]
Dinesh Kumar Dama...
User offline. Last seen 8 years 41 weeks ago. Offline
Joined: 24 Feb 2002
Posts: 68
Dear All,

We have recently recived a schedule from the contractor which was developed in P6 and when we imported it, all the budgeted units were multiplied by 8.

Could anybody advice me on how to fix this?

Thanks & regards

Dinesh

Replies

Dinesh Kumar Dama...
User offline. Last seen 8 years 41 weeks ago. Offline
Joined: 24 Feb 2002
Posts: 68
Hi Arnold,

That worked, Thank you.

Dinesh
Arnold Puy
User offline. Last seen 9 years 39 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Dinesh,

In addition to Anoon info.

According to you that all Budgeted Units were multiplied by 8. If you are using P6 it means that your setting in Edit --> User Preferences --> Time Units tab, "Unit of Time" is in "Hour" just change it to "Days".

Regards,

Arnold
Anoon Iimos
User offline. Last seen 2 years 41 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
that’s the difference between the planning unit used; it may be in Hours or in Days...
Jason Jarrett
User offline. Last seen 15 years 5 weeks ago. Offline
Joined: 29 Sep 2009
Posts: 3
Hello,

You can simply correct the budgeted units by performing a global change. You must be able to filter on the activities needing the change. If interested, let me know & I can walk you through.

Jason