I've been a member for a long time now & found hints & tips very useful, here's my problem.
P6 Nonlabor resource units multiply on import from another datebase.
I used P6 and had to copy my project to a different computer. I have many resources & costs with in the project activities. however when ever I import a project into a "CLEAN" database, (I stress clean to stipulate that it's not already littered with other resource ID's) my NONLABOR resources, UNIT's only, multiply by a factor of 8.
Now as much a I love a riddle, I've had this issue before & found not answer, but as I am on an intrim computer (due to my other onr packing up & waiting a noe one), I do not want to have to re configure all my resources.
My only thought is the 8 hour working day in my calendar, but can find no setting to stop the import multiplyer. this doesn't happen when Export, Import from same database.
anybody any ideas???