Shanmugam Thangam...
User offline. Last seen 4 years 36 weeks ago. Offline
Joined: 3 Feb 2005
Posts: 24
Groups: None
Dears,
In P6 we have done the recovery with cost loaded to expenses category. However the remaining cost shows same as original budgeted cost. ie actual cost or earned value is not deductted.
How I can correct this?

Replies

Ferdinand Fincale...
User offline. Last seen 9 years 21 weeks ago. Offline
Joined: 2 Aug 2008
Posts: 140
Ajith,

Try checking out your calculation settings. Go to projects, calculation tab, then tick on "recalculate actual..." and "link actual..."

Hope it will do.
Arnold Puy
User offline. Last seen 10 years 5 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Ajith,

You need to update your Actual & Earned Value Cost based on the % complete or work done.

Likewise, make sure that in Project Setting under Calculation, mark the check box next to "Subtract Actual from At Completion".

Regards,

Arnold