1. You need to assign manually. The easiest way is to create, organize & define the WBS first before creating activities. Then show the WBS into your activity windows by selecting the Group & Sort, and untick the chechbox next to "Hide if empty". When done, create the necessary activities under the level of each WBS.
If you have already the existing activities then you need to drag that activities or group of activities to that particular WBS. Or you can assign them using Excel sheet.
2. In P6, it is quite complicated because of filter command in the "Bars". First of all, create an Activity Code and assign them to the activities. When, done, go to "Bars" add new & rename the same with the activity code name. In the same window and dialog box, select the filter, select new & modify.
Member for
16 years 5 monthsRE: WBS and Staus Bar appearence
Arnold
Matter sorted. I got info from one PP.
Thanks
Member for
18 years 6 monthsRE: WBS and Staus Bar appearence
Hi John,
For Resources, what do you need?
1. Create
2. Assign
3. Define
4. So on & so forth.
For Earned Value, I think you need to know about the EV technique using WBS IN P6.0
Regards,
Arnold
Member for
16 years 5 monthsRE: WBS and Staus Bar appearence
Arnold
Can you please send me some tips and tricks about Resources and Eraned Value?
Regards,
John
Member for
18 years 6 monthsRE: WBS and Staus Bar appearence
Hi Steve,
Please send me your email address and I will forward to you the steps. My email add is primavera6@live.com
Regards,
Arnold
Member for
16 years 5 monthsRE: WBS and Staus Bar appearence
Arnold,
Thanks for detailed reply.
Is there any way to see those codes which we define in Project Codes in the status bar as we can see and assign in P3?
example: Sec... Dep... Res etc
Secondly how to undue in P6 if u written something wrong?
Please give me tip and tricks to see these defined codes in status bar
Cheers
Member for
18 years 6 monthsRE: WBS and Staus Bar appearence
Hi Steve,
First of all, welcome to PP.
1. You need to assign manually. The easiest way is to create, organize & define the WBS first before creating activities. Then show the WBS into your activity windows by selecting the Group & Sort, and untick the chechbox next to "Hide if empty". When done, create the necessary activities under the level of each WBS.
If you have already the existing activities then you need to drag that activities or group of activities to that particular WBS. Or you can assign them using Excel sheet.
2. In P6, it is quite complicated because of filter command in the "Bars". First of all, create an Activity Code and assign them to the activities. When, done, go to "Bars" add new & rename the same with the activity code name. In the same window and dialog box, select the filter, select new & modify.
Let me know if you have done it.
HTH.
Regards,
Arnold