P6 Baseline Total % not appear when summerize

11 replies [Last post]
Kamarul Bahrin H...
User offline. Last seen 43 weeks 1 day ago. Offline
Joined: 15 Aug 2005
Posts: 23
Dear all P6 expert,


anybody can help me, why total summary % for BASELINE not appear when i summarise or any total % for baseline not appear, I already updated my baseline. only appear Total % for current project only. I cant compare with baseline %. anyone can help me.

Thank you,

KB

Replies

Ayman Eleish
User offline. Last seen 12 years 27 weeks ago. Offline
Joined: 28 Dec 2010
Posts: 48
Groups: None

Dear Kamarul,

You are completely right,in P6 you can not show the summarization of the Baseline,and that was acknowledged by the company themselves.

Realy it is very bad for all planners.

If you are compeled to do the same ,it can be done by using the user defined showing the progress on a summary bar for base line,but it is not in my mind at the time being ,you can search for it at the net.

Ayman

D Artagnan
User offline. Last seen 2 years 29 weeks ago. Offline
Joined: 19 Sep 2008
Posts: 207

This is also my problem. I have tried almost all the options but still in vain.

Maghsoud Joudi
User offline. Last seen 13 years 32 weeks ago. Offline
Joined: 15 Nov 2004
Posts: 9
use "performance progress%".
but to be carefull about unit cost in Base line and current plans. it will affect the summary% and also current%!!!
Kamarul Bahrin H...
User offline. Last seen 43 weeks 1 day ago. Offline
Joined: 15 Aug 2005
Posts: 23
Dear Arnold,

Do you have any solution for this problem.? P6 software problem...

tq
Arnold Puy
User offline. Last seen 9 years 34 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Kamarul,

Yes you are right. BL % Complete for (Activity, Duration, Costs & Units) does not roll-up in the summary band only Schedule % Complete.

Regards,

Arnold
Arnold Puy
User offline. Last seen 9 years 34 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Kamarul,

What Total %age do you mean? If your baseline schedule is cost-loaded, try to add one column the "Schedule % Complete".

Regards,

Arnold
Arnold Puy
User offline. Last seen 9 years 34 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Kamarul,

Let me clear something, there is no (Total Baseline %). For baseline you can show "Schedule % Complete" when you are trying to compare against current (Performance % Complete).

When you are talking about summary, is this the Summary Band in the WBS Level 1?

Not showing anything, you mean it is "BLANK or ZERO"?

Regards,

Arnold
Kamarul Bahrin H...
User offline. Last seen 43 weeks 1 day ago. Offline
Joined: 15 Aug 2005
Posts: 23
Dear Arnold,


Yes no showing anything "Blank".. all BASELINE etc: BL % duration % complete or BL1 if i attached another Baseline. All the total percentage didn’t show anything " Blank" when summarized.

Tq
Kamarul Bahrin H...
User offline. Last seen 43 weeks 1 day ago. Offline
Joined: 15 Aug 2005
Posts: 23
Dear Arnold,

My program is cost loaded. all the total percentage for current appear but for the total baseline not appear when i summarized. I can’t find the error why.
Arnold Puy
User offline. Last seen 9 years 34 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Kamarul,

Is your programme cost-loaded? If not, try to allocate the cost to your baseline as well as your current schedule.

Regards,

Arnold
Kamarul Bahrin H...
User offline. Last seen 43 weeks 1 day ago. Offline
Joined: 15 Aug 2005
Posts: 23
HI arnold,

What i mean is the column for Baseline % (Total Baseline % column ) when i summarise. the total % not show anything.

tq