Open End Activity

6 replies [Last post]
Shahzad Ahmad
User offline. Last seen 15 years 18 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 96

Dear All

Problem related to P6

How i can find out open end activity in Log file.

in logic.... it is not clear at all.

Thanks
Shahzad

Replies

Jenn Weber
User offline. Last seen 11 years 14 weeks ago. Offline
Joined: 20 Jan 2011
Posts: 35
Groups: None

You could also try using the logic analyzer in Acumen Fuse to find all open ended activities (as well as leads, lags, out of sequence activities, reverse logic, redundant, and other logic flaws) within your schedule or in multiple linked schedules.  Visit our website for more information or a free trial of the software: http://www.projectacumen.com/fuse/overview/analysis 

Irfan Khan
User offline. Last seen 28 weeks 23 hours ago. Offline
Joined: 19 Jul 2009
Posts: 138

hi, 

 

run ur project with data date press F9 Press View Log & under SCHEDLOG.notepad u can see Errors:

Warnings: u can find here (Activities without predecessors) (Activities without successors) (Out-of-sequence activities)

(Activities with Actual Dates > Data Date) (Milestone Activities with invalid relationships) etc.

hope it ill be helpfull....

 

regards,,,,
 

Mangesh Khuspe
User offline. Last seen 1 year 6 weeks ago. Offline
Joined: 10 Apr 2007
Posts: 162

Dear Shahzad,

 

There is also another way for that which Rafael and Gary have suggested and can be found at

http://www.planningplanet.com/forums/primavera-version-pm5-pm6/503663/open-link-activity

 

WIth Regards,

 

Mangesh 

Shahzad Ahmad
User offline. Last seen 15 years 18 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 96
Hi Rob

Thanks for reply i found them.


Thanks
Shahzad
Rob Kane
User offline. Last seen 4 years 4 weeks ago. Offline
Joined: 17 Jan 2004
Posts: 27
Groups: None
If you are looking for open ends, stick in your predecessor &successor columns in a layout and run a filter where they = "null"

Rob
Arnel Lagumbay
User offline. Last seen 12 years 19 weeks ago. Offline
Joined: 31 Aug 2008
Posts: 35
Shahzad

Try to tick the"log to file" when you schedule your

programme,there you can find activities w/o

predecessors&successors.

Hope this help..


Best regards,
arnel